S. No. | Construction Work Details | Coefficient |
1 | P.C.C. (1:5:10) | 2.6 Bags/cu.mt. |
2 | P.C.C. (1:4:8) | 3.4 Bags/cu.mt. |
3 | P.C.C. (1:3:6) | 4.4 Bags/cu.mt. |
4 | R.C.C. M-15 (1:2:4) | 6.3 Bags/cu.mt. |
5 | R.C.C. M-20 (1:2:4) | 8.00 Bags/cu.mt. |
6 | R.C.C. M-25 (1:1:2) | 12.20 Bags/cu.mt. |
7 | Brick work in CM (1:6) | 1.32 Bags/cu.mt. |
8 | Brick work in CM (1:4) | 1.90 Bags/cu.mt. |
9 | Half Brickwork in (1:4) | 0.213 Bags/Sq.mt. |
10 | Plastering in CM (1:4) – 15mm thick | 0.131 Bags/Sq.mt. |
11 | Plastering in CM (1:4) – 12mm thick | 0.109 Bags/Sq.mt. |
12 | Plastering in CM (1:4) – 6mm thick | 0.055 Bags/Sq.mt. |
13 | Plastering in CM (1:6) – 15mm thick | 0.086 Bags/Sq.mt. |
14 | Plastering in CM (1:6) – 12mm thick | 0.072 Bags/Sq.mt. |
15 | Plastering in CM (1:6) – 6 mm thick | 0.073 Bags/Sq.mt. |
16 | 20mm thick sand face plastering in two layers. (13 mm thick plaster in CM 1:4 and 7 mm thick plaster in CM 1:2) | 0.220 Bags/Sq.mt. |
17 | Plastering in CM (1:3) – 13mm thick | 0.157 Bags/Sq.mt. |
18 | Plastering in CM (1:4) – 13 mm thick | 0.117 Bags/Sq.mt. |
19 | Plastering in CM (1:3) – 20mm thick | 0.228 Bags/Sq.mt. |
20 | Plastering in CM (1:4) – 20mm thick | 0.170 Bags/Sq.mt. |
21 | Floating coat of neat cement | 0.044 Bags/Sq.mt. |
22 | Brick on edge pitching in CM (1:4) | 0.138 Bags/Sq.mt. |
23 | Brick on edge pitching in CM (1:3) | 0.185 Bags/Sq.mt. |
24 | Flush pointing in brick work with CM (1:3) | 0.031 Bags/Sq.mt. |
25 | 40mm thick Damp proof course in M-20 | 0.32 Bags/Sq.mt. |
26 | 25 mm thick IPS in M-15 | 0.244 Bags/Sq.mt. |
27 | 40 mm thick IPS in M-15 | 0.340 Bags/Sq.mt. |
28 | 50mm thick granite flooring, 1st layer 35mm thick (1:1.5:3), 2nd layer 15 thick (1:2) | 0.433 Bags/Sq.mt |
29 | 125mm high plaster skirting in CM (1:3) | 0.034 Bags/R.M. |
30 | 25mm thick kota stone over 20mm thick bedding in CM (1:6) | 0.24 Bags/Sq.mt. |
31 | 40mm thick kota stone over 20 mm thick bedding in CM (1:6) | 0.264 Bags/Sq.mt. |
32 | 18mm thick kota stone over 12 mm thick bedding in CM (1:6) | 0.264 Bags/Sq.mt. |
33 | 6 mm thick glazed tiles fixing | 0.088 Bags/Sq.mt. |
34 | 25mm thick CM screed in CM (1:5) | 0.218 Bags/Sq.mt. |
35 | 20mm thick mosaic tiles over 25mm thick bedding in CM (1:6) | 0.228 Bags/Sq.mt. |
36 | 18mm thick mosaic tiles over 20mm thick bedding in CM (1:6) | 0.200 Bags/Sq.mt. |
37 | 18mm thick marble skirting over 12mm thick bedding in CM (1:6) | 0.160 Bags/Sq.mt. |
38 | Water Proofing treatment with 50mm thick screed in CM (1:5), 115 thick brick bats in CM (1:3), third layer of 25 mm thick in CM (1:3) | 1.18 Bags/Sq.mt. |
39 | Fixing of rainwater Pipes | |
110 mm diameter PVC | 0.048 Bags/Opening | |
160mm diameter PVC | 0.075 Bags/Opening | |
40 | Joining & Fixing of CI rainwater Pipes | |
100 mm diameter | 0.176 Bags/100 mtr. | |
150 mm diameter | 0.264 Bags/100 mtr. | |
41 | Fixing wooden Frame/Steel frame doors in M-15 concrete of block size. 350 x 100 x 100 mm | 0.129 Bags/Door |
42 | Fixing of steel louvers/windows in M-15 grade concrete of block 150 x 50 x 50 at 750 mm c/c. | 0.008 Bags/Sq.mt |
43 | Fixing of rolling shutters. | 0.70 Bags/ 100 Sq.Mt. |
44 | Providing and Fixing of 50mm thick RCC jali. | 0.329 Bags/Sq.mt. |
45 | Fixing of 50 mm thick RCC Jali. | 0.051 Bags/Sq.mt. |
46 | Fixing of glazed earthen ware Orissa pan type water closet. | 0.5 Bags/No’s |
47 | Fixing of white glazed EWC. | 0.05 Bags/No’s |
48 | Fixing of large flat back urinal. | 0.03 Bags/No’s |
49 | Fixing of hand wash basin/sink | 0.03 Bags/No’s |
50 | Fixing of floor trap of 100/100 mm | 0.05 Bags/No’s |
51 | Jointing and fixing of soil waste Pipe. | |
80mm diameter. | 0.132 Bags/RM | |
100mm diameter. | 0.176 Bags/RM | |
150mm diameter. | 0.264 Bags/RM | |
52 | Fixing of GI water pipes concealed work. | |
15 mm diameter | 0.642 Bags/100M | |
20 mm diameter | 0.770 Bags/100M | |
25 mm diameter | 0.90 Bags/100M | |
32 mm diameter | 0.96 Bags/100M | |
53 | Construction of brick masonry valve chambers of size 300 x 300 x 600 mm CM (1:4) fixing cover in M-15 concrete, M-15 foundation concrete 13mm thick plaster on inside & outside exposed surface. | 0.700 Bags/No’s |
54 | Construction of brick masonry inspection chamber of size 750 x 750 x 1000 mm in CM (1:4) RCC of M-15, 13mm plastering in CM (1:3). | 5.0 Bags/No’s |